Requesting an Inspection
- When making an inspection request you must provide your Building Permit Number, Name of project, Address of Project, and your name telephone number in addition to type of inspection requested
- Inspections must be requested no later than the day before they are needed.
- If the inspection does not meet code at time of inspection or one we cannot enter at time of inspection, will be billed a $25.00 re-inspection fee. This must be paid prior to Power being turned on and before a C.O. will be issued.
- Your Building Permit Card Must be posted at the site in clear view and protected from the weather prior to any inspections!
- To request an inspection you must Call Monday-Friday between 8:30 A.M. and 4:30 P.M. (Voice mail inspection requests are not accepted)
Required Inspections
-
Footing Inspections
-
Electrical Rough In and Final
-
Slab Inspections
-
Plumbing Rough In and Final
-
Under Slab Plumbing
-
HVAC Rough In and Final
-
Under Slab Electrical
-
Commercial Celing/Wall Cover Up
-
Framing Inspection
-
Gas Test
-
Parking
-
Drywall Fasteners
-
Drainage/Landscaping
-
Final Inspection for CO